A01. Appoint the Sponsor

This activity is part of the Preparing section of the Project Flow. Preparation starts as soon as you have the idea or offer for the project, and ends with the decision to execute/accept the project, or drop it. Checking the feasibility or possible options for the project happens in this section as well.

The first thing you need to do is to appoint a person as the Sponsor for the project; a senior manager (preferably a board member) who:

  • Owns the project outcome
  • Funds and resources the project
  • Makes high-level decisions for the project

The Project Manager reports to this person.

The amount of time needed from a Sponsor is minimized in the flow, as senior managers are usually busy. They should be able to spend 5 to 10 hours per month on the project after the Preparation, and up to 30 hours for Preparation.

Preparing

  • A01. Appoint the Sponsor
  • A02. Prepare the Project Summary
  • A03. Appoint the Project Manager
  • A04. Set up the PMIS
  • A05. Appoint the rest of the team
  • A06. Populate the PMIS
  • A07. [Select suppliers and agree on the Supplier PMs]
  • A08. Preparation Audit
  • A09. Go/No-Go
  • A10. Project kick-off
  • A11. Focused Communication

Cycle Planning

  • A12. Update the PMIS
  • A13. [select suppliers and agree on the Supplier PMs]
  • A14. Go/No-Go
  • A15. Cycle kick-off
  • A16. Focused Communication

Weekly Activities

  • A17. Measure and report performance
  • A18. Manage deviations
  • A19. Weekly kick-off
  • A20. Weekly Audit
  • A21. Focused Communication

Daily Activities

  • A22. Capture RICs
  • A23. React to RICs, based on Delegation Limits
  • A24. Accept completed products from the Team Leaders and Supplier PMs

Cycle Closing

  • A25. Evaluate the customer and team satisfaction
  • A26. Plan for improvements
  • A27. Focused Communication

Closing

  • A28. Receive approval and hand over the product
  • A29. Handover the Business Case to the responsible person
  • A30. Evaluate the customer and team satisfaction
  • A31. Closing Audit
  • A32. Archive the PMIS
  • A33. Celebrate and announce closure
  • A34. Focused Communication

Post-Project

  • A35. Check the Business Case and evaluate the benefits
  • A36. Design additional activities if required
  • A37. Focused Communication

Shortcuts

About PMIS elements (documents)

  • A04. Set up the PMIS
  • A06. Populate the PMIS

About Roles (people)

  • A05. Appoint the rest of the team

About Planning

  • A06. Populate the PMIS
  • A12. Update the PMIS