A18. Manage deviations

This is a weekly activity. You can repeat the weekly activities in a certain day of the week (e.g. every Monday). Remember that A17 to A21 should be run in sequence. 

The purpose of measuring progress is to find deviations and fix them.

The forecasts for time and cost are compared to the targets in the Progress Register. If there are deviations, you should compare them with Plan Limits. If both time and cost forecasts are below their Plan Limits, then the Project Manager decides on how to fix them. Otherwise, it means that you cannot meet the targets, and you should find a serious way for fixing the problems. The issue should be escalated to the Sponsor, and everyone checks the possible solutions. When the Sponsor selects a solution, it will be reflected to the plans using the Cycle Planning activities (A12 to A16).

Preparing

  • A01. Appoint the Sponsor
  • A02. Prepare the Project Summary
  • A03. Appoint the Project Manager
  • A04. Set up the PMIS
  • A05. Appoint the rest of the team
  • A06. Populate the PMIS
  • A07. [Select suppliers and agree on the Supplier PMs]
  • A08. Preparation Audit
  • A09. Go/No-Go
  • A10. Project kick-off
  • A11. Focused Communication

Cycle Planning

  • A12. Update the PMIS
  • A13. [select suppliers and agree on the Supplier PMs]
  • A14. Go/No-Go
  • A15. Cycle kick-off
  • A16. Focused Communication

Weekly Activities

  • A17. Measure and report performance
  • A18. Manage deviations
  • A19. Weekly kick-off
  • A20. Weekly Audit
  • A21. Focused Communication

Daily Activities

  • A22. Capture RICs
  • A23. React to RICs, based on Delegation Limits
  • A24. Accept completed products from the Team Leaders and Supplier PMs

Cycle Closing

  • A25. Evaluate the customer and team satisfaction
  • A26. Plan for improvements
  • A27. Focused Communication

Closing

  • A28. Receive approval and hand over the product
  • A29. Handover the Business Case to the responsible person
  • A30. Evaluate the customer and team satisfaction
  • A31. Closing Audit
  • A32. Archive the PMIS
  • A33. Celebrate and announce closure
  • A34. Focused Communication

Post-Project

  • A35. Check the Business Case and evaluate the benefits
  • A36. Design additional activities if required
  • A37. Focused Communication

Shortcuts

About PMIS elements (documents)

  • A04. Set up the PMIS
  • A06. Populate the PMIS

About Roles (people)

  • A05. Appoint the rest of the team

About Planning

  • A06. Populate the PMIS
  • A12. Update the PMIS