A24. Accept completed products from the Team Leaders and Supplier PMs

This is a Daily Activity; the way a Project Manager continuously contributes to the project, and teams.

Deliverables assigned to Team Leaders and Supplier PMs can be completed any day, and that’s time for a quick review and approval by the Project Manager.┬áThe approval in this activity is preliminary. The Project Manager shouldn’t be afraid of approval, as it slows down the project.

Large amounts of work-in-progress is a common problem in projects. It reduces the predictability of the project, takes more resources, and usually lowers quality. It’s best to limit it, and have a clear activity for receiving and approving the deliverables.

 

Preparing

  • A01. Appoint the Sponsor
  • A02. Prepare the Project Summary
  • A03. Appoint the Project Manager
  • A04. Set up the PMIS
  • A05. Appoint the rest of the team
  • A06. Populate the PMIS
  • A07. [Select suppliers and agree on the Supplier PMs]
  • A08. Preparation Audit
  • A09. Go/No-Go
  • A10. Project kick-off
  • A11. Focused Communication

Cycle Planning

  • A12. Update the PMIS
  • A13. [select suppliers and agree on the Supplier PMs]
  • A14. Go/No-Go
  • A15. Cycle kick-off
  • A16. Focused Communication

Weekly Activities

  • A17. Measure and report performance
  • A18. Manage deviations
  • A19. Weekly kick-off
  • A20. Weekly Audit
  • A21. Focused Communication

Daily Activities

  • A22. Capture RICs
  • A23. React to RICs, based on Delegation Limits
  • A24. Accept completed products from the Team Leaders and Supplier PMs

Cycle Closing

  • A25. Evaluate the customer and team satisfaction
  • A26. Plan for improvements
  • A27. Focused Communication

Closing

  • A28. Receive approval and hand over the product
  • A29. Handover the Business Case to the responsible person
  • A30. Evaluate the customer and team satisfaction
  • A31. Closing Audit
  • A32. Archive the PMIS
  • A33. Celebrate and announce closure
  • A34. Focused Communication

Post-Project

  • A35. Check the Business Case and evaluate the benefits
  • A36. Design additional activities if required
  • A37. Focused Communication

Shortcuts

About PMIS elements (documents)

  • A04. Set up the PMIS
  • A06. Populate the PMIS

About Roles (people)

  • A05. Appoint the rest of the team

About Planning

  • A06. Populate the PMIS
  • A12. Update the PMIS