A29. Handover the Business Case to the responsible person

This activity is part of the Closing section, when we're done with the project, or we want to cancel it. In both cases, we need to do a few final things. 

You shouldn’t forget the project after it’s finished. Normally, it’s the responsibility of the program or portfolio management system to take care of the Post-Project activities. If you have such a system, you’ll hand over the Business Case to them, and ignore the Post-Project Activities. Otherwise, the Sponsor remains responsible for the Post-Project activities for 2 to 5 years, depending on the project.

Preparing

  • A01. Appoint the Sponsor
  • A02. Prepare the Project Summary
  • A03. Appoint the Project Manager
  • A04. Set up the PMIS
  • A05. Appoint the rest of the team
  • A06. Populate the PMIS
  • A07. [Select suppliers and agree on the Supplier PMs]
  • A08. Preparation Audit
  • A09. Go/No-Go
  • A10. Project kick-off
  • A11. Focused Communication

Cycle Planning

  • A12. Update the PMIS
  • A13. [select suppliers and agree on the Supplier PMs]
  • A14. Go/No-Go
  • A15. Cycle kick-off
  • A16. Focused Communication

Weekly Activities

  • A17. Measure and report performance
  • A18. Manage deviations
  • A19. Weekly kick-off
  • A20. Weekly Audit
  • A21. Focused Communication

Daily Activities

  • A22. Capture RICs
  • A23. React to RICs, based on Delegation Limits
  • A24. Accept completed products from the Team Leaders and Supplier PMs

Cycle Closing

  • A25. Evaluate the customer and team satisfaction
  • A26. Plan for improvements
  • A27. Focused Communication

Closing

  • A28. Receive approval and hand over the product
  • A29. Handover the Business Case to the responsible person
  • A30. Evaluate the customer and team satisfaction
  • A31. Closing Audit
  • A32. Archive the PMIS
  • A33. Celebrate and announce closure
  • A34. Focused Communication

Post-Project

  • A35. Check the Business Case and evaluate the benefits
  • A36. Design additional activities if required
  • A37. Focused Communication

Shortcuts

About PMIS elements (documents)

  • A04. Set up the PMIS
  • A06. Populate the PMIS

About Roles (people)

  • A05. Appoint the rest of the team

About Planning

  • A06. Populate the PMIS
  • A12. Update the PMIS