A step-by-step guide to P3pper

27. Too much detail?

You can break down Software to its building elements as we did before, and you’ll get something like this:

Seems fine. What about their dependencies?

We can proceed as before, and identify and add dependencies for these as well, but isn’t that too much detail? Instead, we can have a simple list of items, to make sure we won’t forget any of them, and to be able to measure progress, and let the people who are supposed to do it determine in which sequence to work. This makes sense, especially because these small items don’t impact anything outside their parent deliverable.

P3pper doesn’t force you to schedule the whole plan, and you can decide to leave the details of some parts to improvisation. Let’s do that next!


Next: 28. Improvising!

Previous: 26. Duration of parents

Table of contents 01. Creating a user account
02. The blank slate!
03. The first organization
04. The organization page
05. Missing description!
06. Your life...
07. Describing a company
08. Adding the first portfolio
09. Creating a new project
10. Describing the project
11. Setting the start date of the project
12. Setting the duration
13. Adding the second project
14. Navigating items
15. The breadcrumb
16. Identifying deliverables
17. Adding deliverables
18. Adding the remaining deliverables
19. Adding multiple items
20. Importing mind maps
21. Deleting items
22. Adding dependencies
23. Checking the dependencies
24. Going deeper!
25. Going into the details
26. Duration of parents
27. Too much detail?
28. Improvising!
29. Setting durations
30. Small deliverables
31. Moving on...
32. Multiple dependencies
33. Breaking down the training program
34. Adding an event
35. All the past projects
36. Improvisation, again!
37. Dynamic scope items
38. Symbols for item types
39. Adding stakeholders
40. Access level 7
41. Higher level access
42. Multiple levels of access
43. Custodians
44. Finishing the initial plan
45. Plan for this month
46. The tracking section
47. Updating status
48. More about status
49. Adjusting actual dates
50. The next month
51. Progress
52. Forecasts
53. Weights
54. Determining weights
55. Two months later
56. The problem
57. A risk
58. Navigating follow-up actions
59. Closing follow-up items
60. Too many follow-up items
61. Too many tracking items?
62. Progress of dynamic-scope items
63. External dependencies
64. External dependencies without access
65. DONE!