OK, we’ve prepared a simple plan for our Document management system implementation project. This is how it looks like at this point:
Check out the top of the page, below the title of the project; it tells us that this project, which is scheduled to start in 2021-5½ (that’s what you set in the earliest start
field of the project) will finish in 2021-11½ based on the current schedule. That’s about 6 months.
Does it match the initial expectations that you’ve documented in the description
? If not, you either have to talk to the sponsor and revise the goals, or find a way to shorten the current schedule.
Let’s assume that the current schedule is fine.