So, our main issue in the project is Alfresco › Design. You go and ask the custodian
of design about it, and she tells you that the executives in the company insist that the team should wait for their input before they start designing. On the other hand, the executives never have enough time to get together and generate the input.
When there’s an issue, it’s a good idea to document it. To do so, open design and then go to its follow-ups
section. Click on the Add Follow-Up Action button to create a new item.
You can describe the issue like this:
- Cause: Executives have not met to prepare the input for our design.
- Effect: We are not allowed to start designing.
- Impact: This deliverable and other deliverables that are dependent on it are very late. This delays the whole project.
- Response: ?!
Now you can see the follow-up item
in this deliverable, and all its ancestors, including the project itself.
Next, you have to brainstrom with your team and find a good solution for this problem. When you do, record it in the response
field, and assign a team member as the custodian
for the item, to follow-up on that and make sure it’s done.