A17 Measure and report performance

List of all activities

Successor(s):


We measure the progress of the project in this activity, using the Schedule Model and Progress Register. This information will be used to manage deviations in the next activity.

These are the steps for measuring progress:

Using the online dashboard is preferred, but if some stakeholders are not comfortable with it, save a PDF and email it to them.

Avoid too much detail in progress measurement, as it distracts everyone, and doesn’t provide real additional value. The Project Manager may need extra details for finding solutions to recover from deviations and prevent similar problems in the future, which will be provided by the PM Support, but they are not part of the standard measurements and dashboards.

X

Subscription

You can subscribe to the P3.express list to stay informed of future updates. Members of the list are also involved in the future updates and can contribute in different forms.