Assuming that we’re done with the building elements
of the New server, we also need to set their durations. Durations are set for the lowest level deliverables that are not Priority-based (improvised)
, and in our case, it’s the Specifications, Hardware, and Software.
At the beginning, they all have the default duration of 1 half-month
. Let’s say you work in a large organization with a complicated procurement process, and it takes 3 half-months
to buy the hardware. Open Hardware and change its duration to 3.
Then, let’s say the team is going to use a new set of software applications, and therefore, they believe that it takes 2 half-months
. Set the duration.
This is what we get:
However, what if you’re really fast and capable of completing all these three deliverables in only a few days? How would you set that up in P3pper?