We have 6 items to enter underneath Old documents, and from our discussion about the Software deliverable, you remember that in cases like this, where the sequence of work is unimportant or unknown, we should use a priority-based (improvised)
sequence. When there are improvised
items below a deliverable, we should also set the duration of that item; so, let’s give old documents a duration of 4 half-months
. This is what we get:
This is fine for now. However, there’s a big difference between old documents and other deliverables such as software. Can you tell what?