Note: From this point on, we’re going to assume that some time has passed and we moved on. However, P3pper doesn’t accept arbitrary dates, and the only way for doing this, if you don’t want to actually wait for a long time, is to bring the project back in time by decreasing the earliest start
, actual start
, and actual finish
date of all items. I’m simulating the passage of time by doing this.
One month later, and this is the situation:
Both the chart and the tracking
section show that we are supposed to work on hardware and design. Let’s say we’ve started hardware in 2021-6 and finished it in 2021-6½. Update the item with this information.
This is the plan after the update:
It means that given the fact that we’ve finished hardware in the second half of June, we can start working on software in June, even though it was originally planned for later.