A01 - Appoint the Sponsor

Note: This is the old version of P3.express. The current version is available here.

The first thing you need to do is to appoint a person as the Sponsor for the project; a senior manager (preferably a board member) who:

The Project Manager reports to this person.

The amount of time needed from a Sponsor is minimized, as senior managers are usually busy. They should be able to spend 5 to 10 hours per month on the project after the Preparation activities, and up to 30 hours for Preparation.